Our on site restaurant is currently undergoing renovation work to give it a new lease of life.

Phase one of the renovation focuses on the far-right hand side of the restaurant by the windows and will create a new hot and cold snack bar. This work starts on Monday 6 March and is expected to last around three weeks.

During this phase, there will be reduced seating available and there may be some noise while the work is being carried out.

Phase two will begin immediately following the completion of phase one (around 27 March) where work will take place around the main servery and seating areas as well as the kitchen/prep area. This work is expected to last around six weeks.

To facilitate the second phase of the work, there will be reduced availability of seating and a temporary change to the hot food menu.